What is Pile cut-off Level? Pile Foundation


Pile Cut-off level is the actual level at which the piles below pier are made to be of the same level. The concrete of pile is cut-off at the specified level (given in the specifications or drawings usually around 75 mm) while the steel is kept projected in-to the pile cap to make an effective bond between pile cap and piles.



Reason for pile cut :

For Piles casted in dry bore holes while using temporary casing, piles heads shall be casted to a level a bit above the specified cut-off so that, after cutting or trimming, a sound concrete connection can be made with the pile.