What is Pile cut-off Level? Pile Foundation
Pile Cut-off level is the actual level at which the piles
below pier are made to be of the same level. The concrete of pile is cut-off at
the specified level (given in the specifications or drawings usually around 75
mm) while the steel is kept projected in-to the pile cap to make an effective
bond between pile cap and piles.
Reason for pile cut :
For Piles casted in dry bore holes while using temporary
casing, piles heads shall be casted to a level a bit above the specified
cut-off so that, after cutting or trimming, a sound concrete connection can be
made with the pile.